Tuesday, April 29, 2014
CoBo firmware updates (Nathan)
Overview of PAC 38 responses
Tuesday, April 22, 2014
GET Configuration Program (Daniel)
AT-TPC pulser data analysis (Saul)
Tuesday, April 15, 2014
Noise measurement for GET and AT-TPC (Wolfi)
Tuesday, April 8, 2014
Trigger geometry generation program (Daniel)
Pad position convention update (Tan)
Update on firmware issues (Faisal)
Prototype gas test start (Saul)
Tuesday, April 1, 2014
Commissioning Experiment Overview
Tuesday, March 18, 2014
Commissioning Experiment Status
Tuesday, March 11, 2014
Magnet cooling stopped (Daniel)
Prep for next week's commissioning run
Tuesday, March 4, 2014
Detector gas handling connected
Micromegas pulser test (Daniel)
Tuesday, February 25, 2014
Tuesday, February 18, 2014
Micromegas fitting problem (Daniel)
DAQ trigger/time stamp
Tuesday, February 11, 2014
AT-TPC attached to beamline/Hall probe and source arm installed (Daniel)
Micromegas conditioning started (Saul)
LN2 filling of magnet started (Daniel)
Tuesday, February 4, 2014
Received 1st Micromegas (Daniel)
AT-TPC setup vacuum considerations
DAQ status (Faisal)
Mutant/Firmware issues (Nathan)
Tuesday, January 28, 2014
Micromegas update (Daniel)
ZAP and shielding (Faisal, Daniel)
Firmware update (Nathan)
Tuesday, January 21, 2014
-
Tuesday, January 14, 2014
Micromegas manufacturing timeline (Daniel)
CoBo testing (Faisal)
Tuesday, December 17, 2013
Fusion cross sections for 124Sn experiment (Tan)
Work with Mutant firmware for CoBo (Nathan)
Start on ZAP design (Faisal)
Tuesday, December 10, 2013
Endplate holder fixed (Daniel)
Micromegas attachment discussion
Tuesday, December 3, 2013
Planning for February AT-TPC run
Endplate holder on cart to be fixed (Daniel)
Tuesday, November 26, 2013
Micromegas details (Faisal)
AT-TPC test experiment discussion
Notre Dame 12B results (Saul)
Tuesday, November 19, 2013
Placement of AT-TPC on cradle and cart and in solenoid (Daniel)
Discussion on Micromegas
Tuesday, November 12, 2013
Progress on AT-TPC cart and cradle (Daniel)
Shutter doors being made, discussion on laser holes
Tuesday, November 5, 2013
AT-TPC vacuum test with new copper plates (Daniel)
AT-TPC cart assembly started
124Sn(p,p) data (Tan)
Tuesday, October 29, 2013
AT-TPC vacuum testing (Daniel)
Tuesday, October 22, 2013
End plate modifications (Daniel)
CoBo's received
Tuesday, October 15, 2013
AT-TPC chamber pumping test (Daniel)
AsAd cooling discussion
Tuesday, October 8, 2013
End flange seal mounted, plan to pump detector (Daniel)
Tuesday, October 1, 2013
AT-TPC assembly, Field cage, HV contact, accelerator tube assembled (Daniel)
Micromegas traces (Faisal)
ANL resonance histogram (Tan)
Tuesday, September 24, 2013
Accelerator tube and cathode assembly update (Daniel)
10Be angular distributions (Adam)
STPC GET test results (Genie)
Tuesday, September 17, 2013
Field cage and accelerator tube assembly update (Daniel)
STPC GET test (Zibi)
Tuesday, September 10, 2013
Accelerator tube assembly and last potential ring connection (Daniel)
10Be analysis update (Adam)
Tuesday, August 27, 2013
AT-TPC detector assembly (Daniel)
3 AsAd test (Nathan)
Tuesday, August 20, 2013
LHe liquifier received (Daniel)
Assembly plans, leak checking going on (Daniel)
ANL analysis update (Tan)
Micromegas, CoBo firmware update (Faisal, Nathan)
Tuesday, August 13, 2013
Notre Dame experiment summary (Tan)
Update on AT-TPC parts (Saul)
CoBo firmware update (Nathan)
Discussion on tracking and visualization
Tuesday, July 23, 2013
CoBo network and memory performance (Faisal)
ND experiment prep (Saul)
Test chamber results (Maxime, Elodie)
Fission data analysis (Guillaume, Cathleen)
Tuesday, July 16, 2013
Detector field cage assembly (Daniel, Josh)
CoBo ethernet and firmware (Faisal, Nathan)
ANL experiment analysis update (Tan)
Test chamber fission measurement (Cathleen, Guillaume)
Tuesday, July 9, 2013
Detector cathode assembly (Daniel, Josh)
CoBo firmware update (Faisal, Nathan)
Discussion about upcoming ND alpha decay run
Cf source holder (Maxime)
Tuesday, July 2, 2013
AT-TPC fabrication update (Daniel)
ANL analysis update (Tan)
Cf source measurements (Cathleen, Guillaume)
Tuesday, June 25, 2013
Neural network work (Josh)
10Be analysis (Adam)
CoBo testing (Faisal)
3-body decay charge deposit calculations (Guillaume)
Tuesday, June 18, 2013
Introduction of 3 new students (Daniel)
Field cage development update (Daniel)
Summer experiment at Notre Dame (Saul)
Laser testing results with test chamber (Maxime)
Alpha range calculation for 12C 3-alpha decay (Guillaume)
CoBo firmware update (Faisal)
Multiplicy trigger update (Nathan)
Measurements with fission source (Wolfi)
Tuesday, May 28, 2013
Field cage development update (Daniel)
Solenoid cooling update (Daniel)
Laser testing results with test chamber (Saul)
Diffusion calculation for 12B experiment (Maxime)
Alpha range calculation for 12C 3-alpha decay (Guillaume)
CoBo firmware update (Nathan)
Tuesday, May 21, 2013
Status of LHe fill of Solenoid (Daniel)
CoBo testing update (Faisal)
12C 3-body decay simulation (Wolfi)
Laser testing started (Saul)
Tuesday, May 14, 2013
m-CoBo update, DDR2 memory, Flash, etc. test (Faisal)
ANL analysis update (Tan)
AT-TPC fabrication update (Daniel)
Transfer LN2 to LN2 shield from He vessel (Daniel)
Tuesday, May 7, 2013
Solenoid cooling status (Daniel)
Laser safety review and future test plans (Saul)
CoBo testing update (Daniel)
Tuesday, April 30, 2013
CoBo shipping update (Daniel)
10Be analysis update (Adam)
Solenoid cooling started (Daniel)
ANL upcoming experiment update (Tan)
Work started on UV laser (Wolfi)
Tuesday, April 23, 2013
Field cage update (Daniel)
Experiment plans, ANL, Notre Dame
Diode protection circuit discussion
Update on time differences for ANL data (Tan)
Tuesday, April 16, 2013
Field cage measurements (Daniel)
ANL data sorting (Tan)
CoBo Power (Faisal)
Tuesday, April 9, 2013
Field cage cleaned (Daniel)
ANL experiment magnetic field considerations
plan to cool solenoid (Daniel)
firmware adapting to full CoBo (Faisal)
CoBo clock architecture (Faisal)
Tuesday, April 2, 2013
124Sn Argonne test run update (Daniel)
Field cage machined and received
CoBo v.0.2 memory (Faisal)
Gas handling update (Zach M)
Tuesday, March 12, 2013
10Be data analysis update (Adam)
ANL experiment details (Tan)
progress on multiplicity trigger (Nathan, Tan)
Tuesday, March 5, 2013
ANL experiment details (Tan)
discussion on multiplicity trigger, sparking limit for Sn beams at ANL
CoBo design update (Faisal)
AsAd's ordered (Daniel)
Discussion of card shielding
Tuesday, February 26, 2013
ANL experiment scheduled (Tan)
Multiplicity trigger discussion
CoBo progress (Faisal)
Tuesday, January 22, 2013
AT-TPC Project Timeline (Daniel)
Notre Dame experiment prep
CoBo memory debugging (Faisal)
Tuesday, January 15, 2013
CoBo work, VxWorks image generation (Faisal, Shelbi, Patrick)
Discussion of mesh signals for fission fragments
Tuesday, January 8, 2013
New Micromegas update
Notre Dame experiment scheduled
Tuesday, December 11, 2012
Field cage received (Daniel)
Drawings submitted to shop
Cobo development update (Faisal)
Prototype Micromegas design update (Saul)
Tuesday, December 4, 2012
GET controller and Micromegas testing (Tan, Ian)
Micromegas design update (Faisal)
Tuesday, November 27, 2012
AT-TPC event generator (Daniel)
GET software update (Tan, Nathan)
Prototype Micromegas pad design (Saul)
Cobo Gigabit ethernet (Faisal)
Tuesday, November 20, 2012
Detector drawing almost approved (Daniel)
Prototype Micromegas Pad design (Saul)
CoBo Gigabit work (Faisal)
Tuesday, November 13, 2012
AT-TPC cart design (Daniel)
GET Controller software updated (Nathan)
Tuesday, November 8, 2012
Plans to order AGET chips (Daniel)
GET debugging (Nathan)
Tuesday, October 30, 2012
AT-TPC fabrication progress (Daniel)
Gas handling update (Zach)
Tuesday, October 23, 2012
Tuesday, October 16, 2012
Tuesday, October 9, 2012
AT-TPC design approval in process (Daniel)
Saclay AsAd 1.1 test after repair (Tan)
CoBo firmware updated for use with multiple reduced CoBo's (Nathan)
MCP testing setup (Adam)
Tuesday, October 2, 2012
Fixed regulator for Saclay AsAd 1.1 (Tan)
Agiltron test (Saul)
Reduced CoBo update (Nathan)
Micromegas PCB update (Faisal)
8Be kinematics (Aimee)
Tuesday, September 25, 2012
Comparison of Daisuke's analysis of 6He elastic scattering data (Aimee)
Saclay AsAd 1.1 testing (Tan, Aimee, Nathan)
CoBo firmware for ethernet frames update (Nathan)
CoBo processor status (Faisal)
Tuesday, September 18, 2012
Field cage fabrication started (Daniel)
Hit pattern and thresholds test for GET (Tan, Aimee)
New pump and compressor update (Zach)
MCP testing setup (Adam)
Pad design (Faisal)
Tuesday, September 11, 2012
AT-TPC source arm design update (Daniel)
Test chamber data, micromegas troubleshooting (Tan, Aimee)
CoBo update and micromegas pad design (Faisal)
Tuesday, September 4, 2012
GET electronics, testing saturation problem (Tan, Aimee)
Gas handling, compressor and pump update (Zach)
10Be analysis (Adam)
Pad design implementation status (Faisal)
Tuesday, August 28, 2012
AT-TPC magnet yoke assembled and put in place (Daniel)
AT-TPC design updates, Gas flow tube size for flow rate (Daniel)
Ring cutter design (Daniel)
GET multiplicity measurements (Tan, Aimee)
Tuesday, August 14, 2012
GET testing update (Tan, Aimee)
10Be analysis (Adam)
Field cage ring construction (Ian, Wolfi)
CoBo update (Faisal)
Tuesday, August 7, 2012
Fission source measurements (Remi, Malek, Tan)
GET software problems
Pad plane design, research on laser, AT-TPC Mechanical Design Review (Saul)
10Be + alpha data analysis update (Adam)
CoBo, DDR memory testing (Faisal)
Tuesday, July 31, 2012
Problems and progress on fission source measurement in test chamber (Remi, Malek, Tan)
CoBo update (Faisal)
Tuesday, July 24, 2012
Micromegas pad pattern with fine pitch area (Saul)
8Be statistics update (Aimee)
Tiled micromegas data taking and mapping (Remi, Malek, Tan)
GET electronics testing (Wolfi, Tan)
CoBo testing/ZAP update (Faisal)
Tuesday, July 17, 2012
More data taken for tiled resitive micromegas (Malek, Remi, Tan)
Gas tube progress (Ian)
Prototype CoBo boards received (Faisal)
Tuesday, July 10, 2012
Tiled micromegas measurements (Malek, Remi, Tan)
10Be angle measurements (Adam)
CoBo and ZAP update (Faisal)
Tuesday, July 3, 2012
Considerations for ZAP/AsAd mounting, shielding, cooling
GET electronics testing started (Tan, Faisal)
Micromegas pad design considerations (Saul)
Allene test results (Malek, Remi)
Tuesday, June 26, 2012
Endplate design details (Daniel)
10Be + 6He analysis (Adam)
Gas handling parts ordered (Zach)
Plan for gas tubes for Prototype (Ian)
GET software installation and testing plans (Tan, Daniel)
Pad simulation update (Saul)
Tuesday, June 19, 2012
Allene measurements (Malek, Remi)
8,9Be analysis (Aimee)
MCP housing modifications (Adam)
CoBo update (Faisal)
Tuesday, June 12, 2012
Pad geometry simulation (Saul)
GET software update (Nathan)
CoBo and ZAP update (Faisal)
Tuesday, June 5, 2012
Allene testing (Malek, Remi, Tan)
Micromegas pad simulation results (Saul)
Be analysis (Aimee)
ZAP design (Faisal)
Tuesday, May 29, 2012
End plate developments (Daniel)
Gas mixture (Ar-H2) measurements (Malek, Remi, Tan)
Be fusion analysis (Aimee)
ZAP design (Faisal)
Tuesday, May 22, 2012
End plate prototype (Daniel)
Physics discussion meetings to start
Thursday, May 10, 2012
Solenoid enclosure and magnetic field considerations (Daniel)
ZAP design considerations (Daniel)
GET raw data unpacking (Tan)
CoBo quotes (Faisal)
Agiltron micromegas testing (Saul, Wolfi)
Thursday, May 3, 2012
ATTPC final design almost ready. HV was ordered this morning. (Daniel)
Gas handling system (Zach)
Test with micromegas from Agiltron (Wolfi)
Conditioning of micromegas, simulation progress (Saul)
Board designed about to be submitted (Faisal)
9Be and 8Be (Aimee)
Repairing MCP housing, root code (Adam)
Thursday, April 25, 2012
GET software fully compiled in MAC (Nathan is fixing some bugs) (Daniel)
Gas handling system (Zach/John)
Shielding of the solenoid (Wolfi)
Conditioning of micromegas (Saul)
SBIR will send commercial micromegas to test (Wolfi)
9Be and 8Be (Aimee)
Repairing MCP housing (Adam)
Thursday, April 19, 2012
Power supply quote (Daniel)
Conditioning of micromegas (Tan and Saul)
Mapping on the way while waiting for the connectors to arrive (Daniel and Ian)
Mechanical design almost ready. Working in a transportation cart for the detector (Daniel)
9Be and 8Be (Aimee)
Simulation in progress (Saul)
Dineutron FRESCO simulation (Adam)
Thursday, April 12, 2012
AGET, AsAd update and plans for testing (Nathan)
Proposal for fission studies with Prototype (Bill)
Thursday, April 5, 2012
AsAd pinout (Nathan)
Plans for conditioning micromegas and test electronics
Discussion on programmable ZAP
Magnet yoke, fringe field calculations underway (Daniel)
Search for 8Be (Aimee)
Thursday, March 29, 2012
Power supply quotes (Daniel)
Search for 9Be (Aimee)
Discussion on amplifiers and linear circuits
Gas handling system update (Zach)
COBO update (Faisal)
Thursday, March 23, 2012
AT-TPC flange design (Daniel)
AGET testing and COBO progress (Nathan, Faisal)
Micromegas pad design considerations (Saul)
Thursday, March 1, 2012
Solenoid field calculations (Daniel)
ND experiment Prep
AGET testing update (Nathan)
Thursday, February 23, 2012
Samurai TPC pad plane (Jon Barney)
AT-TPC flange design (Daniel)
Allene test results (Tan)
6He data analysis (Aimee)
ND experiment trigger (Wolfi)
Thursday, February 16, 2012
Prep for ND experiment
Ar + H2 tests (Tan, Saul)
COBO DDR update (Faisal)
Wednesday, February 8, 2012
Prep Issues for ND experiment, adapter piece for MCP/Prototype (Adam, Tan)
COBO update (Faisal)
Gas Handling update (Zach)
Thursday, February 3, 2012
Update from Bob Flight on AT-TPC design (Daniel)
Adaptor Board status (Tan, Ian)
AGET testing update (Nathan)
Gas Handling update, discussion of need for recirculation and gas chromatagraph (Zach, John)
Thursday, January 26, 2012
NIM signal to T2K test (Tan)
Resistive Micromegas Adapter board (Ian)
COBO, crate setup (Faisal)
Gas handling system update (Zach)
Thursday, January 19, 2012
Ar + H2 mixture test results (Wolfi, Tan, Ian)
Notre Dame experiment scheduling and needs
AGET testing to be planned (Nathan)
COBO update, issues with DDR memory (Faisal)
Gas handling system requirements (John)
ND date analysis (Adam, Aimee)
Thursday, January 12, 2012
Test of resistive micromegas, Adapter board (Tan, Ian)
Plan for Ar+H test (Wolfi, Tan, Ian)
some thoughts about ND experiment trigger
Gas handling system update (Zach)
Micromegas pad design
Thursday, January 5, 2012
Agenda
AT-TPC Design update, chamber shortened (Daniel)
Resistive Micromegas Adapter board (Ian)
AGET testing (Nathan)
COBO update (Faisal)
Allene info (Tan)
Thursday, December 22, 2011
Agenda
AT-TPC Design update
COBO, change from 3 to 1 data format (Nathan)
Thursday, December 15, 2011
Agenda
Resistive Micromegas, possibilities for capacitance measurement
Plan to test different gas mixtures (Ar+H, allene), (Ian)
Design of resistive Micromegas adapter board (Ian)
Thursday, December 8, 2011
Resistive Micromegas Simulations (Wolfi)
GET meeting: GET board presented (Faisal)
need to test logic in chip
hit pattern recognition possible?
Thursday, November 3, 2011
Agenda
ND experiment in October (DS)
GET (Nathan)
Thursday, September 15, 2011
Agenda
CoBo (Nathan)
ND experiment in October (DS)
MCP (Adam/Wes)
Thursday, September 08, 2011
Agenda
ND experiment in October (DS)
Design effort/ Gas handling (Daniel)
ND visit & MCP (Adam/Wes)
GET (Nathan)
Testing of Micromegas with pulser(Wolfi)
Thursday, September 01, 2011
Agenda
Test chamber with ZAP/ ND experiment in October (DS)
PCB for MCP (Adam/Wes)
CoBo (Nathan)
Thursday, August 25, 2011
Thursday, August 11, 2011
Agenda
Test chamber with ZAP (DS)
CoBo (Nathan)
Analysis of ND fusion data (Aimee)
Gas handling system (John)
Thursday, August 4, 2011
Agenda
Analysis of ND data (DS)
CoBo (Nathan)
Analysis of ND fusion data (Aimee)
Thursday, July 28, 2011
Agenda
Range analysis for hydrogen (Fred)
Correlation between pads of Micromegas (Fabien)
New AsAd board (Nathan)
MCP (Adam)
Resistive Micromegas (Wolfi)
Thursday, July 21, 2011
Agenda
ReA3 layout (Fernando)
Delay line (Adam/Aimee)
Resistive Micromegas (Wolfi)
Range analysis for hydrogen (Fred)
Correlation between pads of Micromegas (Fabien)
Gas handling system (John)
Spring connector (Bill)
ZAP/Micromegas for Prototype (Wes)
Thursday, July 14, 2011
Agenda
ReA3 layout (Fernando)
Samurai TPC (Rebecca)
CoBo (Nathan/Faisal)
Gas handling system (John)
Correlation between pads of Micromegas (Fabien/Fred)
Thursday, July 7, 2011
Agenda
CoBo (Nathan/Faisal)
Narval (Eugene)
Delay line for the MCP (Adam/Aimee)
Analysis of the hydrogen data / Pad response (Fabien/Fred)
Thursday, June 30, 2011
Agenda
Test of hydrogen (Dany)
Analysis of the hydrogen data (Fabien)
Simulation of the pad responses (Fred)
Narval (Eugene/Fred)
CoBo (Nathan/Faisal/Gilles)
Delay line for the MCP (Adam)
Resistive Micromegas (Aimee)
Thursday, June 23, 2011
Agenda
CoBo/AsAd (Nathan)
uTCA (Faisal)
ND analysis (DS)
Hydrogen test (Dany)
Charge division (Aimee)
Analysis of H2 data (Fred/Fabien)
Thursday, June 16, 2011
Agenda
ND beam monitor / ND analysis (DS)
Hydrogen test (Dany)
Reaction calculation (Adam)
CoBo status (Nathan)
Design of the AT-TPC (Daniel)
Thursday, June 9, 2011
Agenda
ND beam development (DS)
P10 test (Eugene)
MCP (Adam, Aimee)
CoBo status (Nathan)
Thursday, June 2, 2011
Agenda
Test of hydrogen/P10 (Dany)
He+Isobutane/ ND beam development (DS)
MCP (Adam, Aimee)
CoBo status (Faisal)
Thursday, May 26, 2011
Agenda
Preparation for ND fall/ He+Isobutane (DS)
MCP (Adam, Aimee)
AsAd status (Nathan)
CoBo status (Faisal)
Thursday, May 19, 2011
Agenda
Test of hydrogen gas (Eugene, Dany)
Analysis of the Notre Dame data (DS)
MCP (Adam, Aimee)
AsAd status (Nathan)
CoBo status (Faisal)
Gas handling system test (John)
Thursday, May 12, 2011
Agenda
Analysis of the Notre Dame data (DS)
Test of hydrogen gas (Eugene, Dany)
Resistive Micromegas (Wolfi)
MCP (Adam, Aimee)
AsAd status (Nathan)
Thursday, May 5, 2011
Thursday, April 28, 2011
Agenda
Commissioning at Notre Dame(DS)
Thursday, March 17, 2011
Agenda
Schedule of transport(DS)
Upgraded T2K (Eugene)
Reduced CObo (Nathan)
MCP(Adam)
Thursday, March 10, 2011
Agenda
Visit to ND (DS)
Upgraded T2K (Eugene)
Stay at Saclay (Nathan)
MCP(Adam)
Thursday, March 3, 2011
Agenda
Analysis of the wire plane (Lu)
Prototype AT-TPC (DS)
Upgraded T2K (Eugene)
GET (Faisal)
Power Supply (Daniel)
Thursday, February 24, 2011
Agenda
Prototype AT-TPC: Uniformity, time dependence (DS)
Power supply for GET (Eugene)
MCP & beam window foil (Adam)
Visit to Saclay (Nathan)
Gas handling system (John)
Thursday, February 17, 2011
Agenda
ZAP (Mike)
Trigger (Wolfi)
MCP (Adam)
Matsusada Power Supply (Daniel)
Thursday, February 10, 2011
Agenda
The beam line ladder (Mike)
Gas handler (John)
The Prototype AT-TPC (DS)
Reduced Cobo (Nathan)
Upgraded T2K and its support(Eugene)
Cross talk of the PCB (Bill)
Preliminary Project Plan (Daniel)
Thursday, February 3, 2011
Agenda
The Prototype AT-TPC (DS)
Upgraded T2K, grounding of the GET (Eugene)
micro TCA (Faisal, Nathan)
Gas handler (John)
Thursday, January 27, 2011
Agenda
Designing of the AT-TPC (Marius)
The Prototype AT-TPC (DS)
Upgraded T2K, grounding of the GET (Eugene)
Friday, January 14, 2011
Agenda
The Prototype AT-TPC (DS)
Designing of the AT-TPC (Marius)
Designing of the ZAP (Mike)
Status of the Prototype GET (Nathan)
Thursday, January 6, 2011
Agenda
The DAQ, the new T2K (Eugene)
The Prototype AT-TPC (DS)
Designing of the AT-TPC (Marius)
Development of the gas handler (John)
Micro TCA (Faisal)
Status of the Prototype GET (Nathan)
Thursday, December 30, 2010
Thursday, December 16, 2010
Agenda
Update of the Prototype AT-TPC (DS/Eugene)
Commissioning at ND (DS)
New T2K (Eugene)
Status of the stay of Nathan in Bordeaux (Daniel/Faisal)
Thursday, December 9, 2010
Agenda
Update of the Prototype AT-TPC (DS)
DAQ system for the GET (Eugene)
Reduced CoBo update (Faisal)
Thursday, December 2, 2010
Agenda
Update of the Prototype AT-TPC (DS)
Reduced CoBo update (Nathan)
Thursday, November 18, 2010
Agenda
Update of the Prototype AT-TPC (DS)
Design of the AT-TPC (Marius)
Reduced CoBo update (Nathan)
Thursday, November 11, 2010
Agenda
Commissioning at ND (DS)
Reduced CoBo update (Nathan)
Thursday, November 4, 2010
Agenda
Update of testing of the Prototype AT-TPC (DS)
Reduced CoBo update (Nathan)
Design of the Field Cage (Jon)
Thursday, October 28, 2010
Agenda
The cathode power supply issue (DS)
Conditioning of the Micromegas (Mike)
Reduced CoBo update (Nathan)
Testing of the CO2 trap (John/Mike)
Design of the Field Cage (Jon)
Thursday, October 21, 2010
Agenda
Testing of the CO2 trap (Mike)
The control software of power supplies (Eugene)
Assembly of the Prototype AT-TPC (DS/Mike)
Friday, October 15, 2010
Agenda
Report on the visit of CEA-Saclay (Nathan/Eugene)
Thursday, October 7, 2010
Agenda
Assembly of the Prototype AT-TPC (DS)
Thursday, September 30, 2010
Agenda
Micromegas fabrication at Saclay (Mike/Bill)
Progress on assembly of prototype detector (Daisuke)
Thursday, September 23, 2010
Agenda
Cable & remote control of high voltage power supply (Eugene)
Status of fabrication of Micromegas (Daisuke)
Status of hydrogen/deuterium safety (Daisuke)
Status of assembly of Prototype AT-TPC (John/Jon/Daisuke)
Status of testing of the CO2 trap (John)
Reduced CoBo/Prototype GET plan (Nathan)
Thursday, September 16, 2010
Thursday, September 9, 2010
Thursday, September 2, 2010
Thursday, August 26, 2010
Agenda
Progress on prototype fabrication and assembly (Mike)
Cathode voltage feedthru for the AT-TPC (Eugene)
Progress on wire plane tests (Daisuke)
Thursday, August 12, 2010
Thursday, August 5, 2010
Agenda
GET status (Nathan)
Laser calibration system (Justin/Mike)
Gas handling system for the Prototype (DS)
Thursday, July 29, 2010
Agenda
Design of the AT-TPC (Harry)
The status of the analysis of the Micromegas test (Anthony)
Thursday, July 22, 2010
Agenda
Review of the gas handling system of the AT-TPC (John/Ana)
GET power supply / Remote control system (Eugene)
Thursday, July 15, 2010
Agenda
Status of testing of Micromegas (Anthony/Claire)
Status of MCP design (Justin)
Misc. information (DS)
Thursday, July 8, 2010
Agenda
Status of the design of the Prototype (Daisuke)
Status of the new test room (Bill)
Multi-pin connector connection test kit with LED (Mike)
Laser & X-Y table (Mike/Justin)
Misc (Hydrogen gas, Gas handling system review, Power supply)
Thursday, July 1, 2010
Thursday, June 24, 2010
Agenda
review released drawing for the prototype from B. Flight, before sending to J. Ottarson for final design review (Daisuke)
progress on testing of gas mixtures and energy resolution (Claire)
suggestions for organization of test area (Bill)
Announcements (Daniel)
Thursday, June 17, 2010
Agenda
Update of the design of the AT-TPC (Harry)
Status of the test of Micromegas (Claire/Justin/Anthony)
Slides
Thursday, June 10, 2010
Agenda
Update of the design of the Prototype AT-TPC (DS)
Thursday, June 3, 2010
Agenda
Status of move to new testing area and test setup (Daisuke)
Slides
Discussion of milestone dates for prototype (Daisuke/Daniel)
Status of CoBo development (and other DAQ components?) (Nathan)
Thursday, May 27, 2010
Agenda
New test area organization and progress (Daisuke)
Tests of micromegas - resolution with alpha source (Claire)
Slides
Preparation of issues to discuss with Bob Flight at next meeting this coming Friday
Breakdown of AT-TPC project in sub-projects (Daniel)
Thursday, May 20, 2010
Agenda
New test room update
Testing of Micromegas; reduction of negative cross talk
Slides
ANSYS for studying mechanical characteristics of the AT-TPC
Design of Prototype AT-TPC at Rochester
Thursday, May 13, 2010
Agenda
Testing of micromegas in test chamber
Slides
Status of clean room and its infrastructure
Status of connector board prototype
Prototype design at Rochester / organization of follow-up weekly meetings
Possibility of collaboration with Lawrence Livermore National Laboratory
Thursday, May 6, 2010
Agenda
Status of clean room and schedule of move to new testing/assembly area
Slides
Micromegas tests: status and issues
Discussion about a laser calibration system
Slides
Gas handling system design status (feedback on work order, path forward)
Thursday, April 29, 2010
Agenda
Status of clean room (Daisuke)
Slides
Test of micromegas with new connectors (Mike/Daisuke)
Concept drawing for TPC angle mechanism (Harry)
Thursday, April 22, 2010
Agenda
Design of prototype in Rochester (Daisuke)
Gas handling system design (Fernando/Ana)
Clean room construction (Daniel/Daisuke)
Connector assembly prototype (Mike)
Discussion about items that should be procured
ASAP (Bill)
Miscellaneous
Thursday, April 15, 2010
Thursday, April 8, 2010
-
Agenda
The status of the CoBo (NU)
Slides
The individual bias circuit and the insertion test kit of the Micromegas (MF)
Thursday, April 1, 2010
-
Agenda
Micromegas design submission (MF)
Slides
Test field cage (WM)
Status of the project management (DS)
Slides
Forthcoming events (WM)
Thursday, March 25, 2010
-
Agenda
Capacitance measurement of Micromegas (MF)
Slides
Status of the Prototype design (WM/DS)
Thursday, March 18, 2010
-
Agenda
-
-
-
Micromegas capacitance (WM)
Purchasing of a scroll pump (FM/DS)