This is an old revision of the document!
14002:
Before vault:
Get pallets from storage (where do we put them?)
Organize schedule with facilities to install chamber, TMP
Organize, assemble, test electronics (e.g. what kind of XLMs will we use?)
Remove dEs
Test Es and decide on telescope arrangement
Plan out flange mapping
Will there be any detectors running at 2 gains like last time?
Procure an alpha source (does the lab have a new one yet?)
In vault:
Alignment (Dave Sanderson)
Install electronics, test
Clean chamber and get good vacuum
Flush and install chiller
Set up HV crate with proper bias mapping (with WU boxes probably)
Install telescope mount
Install telescopes, cable, hook up cooling carefully
Test setup with alpha source
Setup targets
Align
14009:
Before 14002:
-Think about modifications for dE setup
-Test dE PA box (confirm how many PAs we have that work)
After 14002:
-Remove telescopes, install dEs
-Install dEs (maybe test them first, before removing them for 14002?)
-Will we use a HiRA telescope at 0 deg? If so, we need a mount. If not, we need the detectors as well as a mount and proper electronics. Do we need to worry about radiation damage?
-Install mount at 0 deg, associated electronics, and dE electronics/PA box
-Install HiRA telescopes
-Set up DE bias in HV crate
-Test with alpha source