14002:
Before vault:
In vault: -Alignment (Dave Sanderson) -Install electronics, test -Clean chamber and get good vacuum -Flush and install chiller -Set up HV crate with proper bias mapping (with WU boxes probably) -Install telescope mount -Install telescopes, cable, hook up cooling carefully -Test setup with alpha source -Setup targets -Align
14009:
Before 14002: -Think about modifications for dE setup -Test dE PA box (confirm how many PAs we have that work) After 14002: -Remove telescopes, install dEs -Install dEs (maybe test them first, before removing them for 14002?) -Will we use a HiRA telescope at 0 deg? If so, we need a mount. If not, we need the detectors as well as a mount and proper electronics. Do we need to worry about radiation damage? -Install mount at 0 deg, associated electronics, and dE electronics/PA box -Install HiRA telescopes -Set up DE bias in HV crate -Test with alpha source