This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision Next revision | Previous revision | ||
|
msu:e14009_to-do_list [2016/12/15 16:03] brownk |
msu:e14009_to-do_list [2017/01/17 11:35] (current) brownk |
||
|---|---|---|---|
| Line 22: | Line 22: | ||
| Possible Travel days | Possible Travel days | ||
| - | * Alan (1/11-1/18) | + | * Alan 1/11-1/18, 2/3 |
| - | * Sean/ | + | * Sean/Dan 1/9-1/13 |
| + | |||
| + | Other items - added 1/17 | ||
| + | Implement dE bias for all detectors, test and calibrate dEs | ||
| + | Install 0deg detector, internal cabling | ||
| + | Setup QDC, test - modify readout and other code to accommodate | ||
| + | Install Cu beam blocks - test all | ||
| + | Install targets | ||
| + | Install beam-pipe section | ||