Ordered list of tasks for e14002:
prior to vault access:
Test HINP 4 electronics (10/3)
Edit spectcl for HINP 4 (Kyle, 10/3)
Pulser test MB1 (14 CBs) (Kyle, 10/10)
Test HINP 4 (E) motherboard and HINP 3 (dE) together (Kyle)
Test CsI shaper/disc (Sean/Kuan)
Alpha Tests of HiRA E's (Kyle/Sean, 10/12)
Test dE preamp box (e14009)
Set up HiRA mount (in N2/N3) with dummy detectors (Sean,Kuan)
Test/locate all internal cables with cable tester, remake/fix any lost or broken cables
After access to vault (Nov 1)
Test HiRA target ladder
Work with facilities to get chamber installed (Finished by Nov 12)
Clean chamber and reach functional vacuum (1e-6)
Arrange feed-through flanges as desired and retest vacuum (Nov 12)
Install internal mounting structure (Nov 14)
Assemble the array with HiRA dummies and do rough alignment with transit
Install chiller and cooling water lines inside chamber.
We can test these are leak tight by first pumping with them empty (water blown out with Nitrogen) and then fill with water and retest vacuum. No HiRA detectors inside chamber until this is complete!
Once they have been leak tested these should never be disconnected.
locate computer and desk for vault
Move electronics racks (3, from hira lab) to S2 vault . Connect to chamber feed-through flanges
Test electronics with pulsers
Remove dummies and replace with real telescopes. Align with transit.
Setup and test ISEG bias supply
test the Si detectors with alpha source
test CsI with cosmics
Install and align targets
Set up the logic.