Ordered list of tasks for e14002:
prior to vault access:
Test HINP 4 electronics (10/3)
Test CsI shaper/disc (Sean/Kuan)
Test dE preamp box (e14009, UCONN)
After access to vault (Nov 1)
Test HiRA target ladder
Clean chamber and reach functional vacuum (1e-6)
Install internal mounting structure (Nov 14)
Assemble the array with HiRA dummies and do rough alignment with transit
Install chiller and cooling water lines inside chamber.
We can test these are leak tight by first pumping with them empty (water blown out with Nitrogen) and then fill with water and retest vacuum. No HiRA detectors inside chamber until this is complete!
Once they have been leak tested these should never be disconnected.
Test electronics with pulsers
Remove dummies and replace with real telescopes. Align with transit.
Setup and test ISEG bias supply
test the Si detectors with alpha source
test CsI with cosmics
Install and align targets
Set up the logic.