msu:e14002_to-do_list [2016/09/01 11:27] brownk created |
msu:e14002_to-do_list [2016/11/14 10:07] (current) brownk |
||
---|---|---|---|
Line 2: | Line 2: | ||
prior to vault access: | prior to vault access: | ||
- | | + | - Test HINP 4 electronics (10/3) |
- | | + | * Test HINP 4 (E) motherboard and HINP 3 (dE) together (Kyle, 10/31) |
- | * Integrate HINP4 readout code with NSCL DAQ (Kyle) | + | - Test CsI shaper/ |
- | * Edit spectcl for HINP 4 | + | * Test 5 pico shaper/disc (16 channels each) |
- | * Pulser test MB1 (14 CBs) | + | - Test dE preamp box (e14009, UCONN) |
- | - Test CsI shaper/ | + | |
- | * Test 5 pico shaper/disc (16 channels each) | + | |
- | * Confirm with WU/UCONN if first stage shaper gains need adjustment | + | |
- | - Alpha Tests of HiRA E's | + | |
- | * Determine if/which strips are broken | + | |
- | - Test dE preamp box (e14009) | + | |
* Determine if/which channels are broken | * Determine if/which channels are broken | ||
* Work with WU to integrate ISEG bias | * Work with WU to integrate ISEG bias | ||
- | - Retrieve pallets from offsite storage | + | |
- | - Set up HiRA mount (outside of chamber) with dummies | + | After access to vault (Nov 1) |
- | * locate missing pieces | + | |
- Test HiRA target ladder | - Test HiRA target ladder | ||
- | * Work with Craig Snow to modify | + | * Work with Craig Snow to modify |
- | - Test/locate all internal | + | - Clean chamber and reach functional vacuum (1e-6) |
+ | - Install | ||
+ | * Maintain isolation of internal parts from the chamber walls, test frequently | ||
+ | - Assemble the array with HiRA dummies and do rough alignment with transit | ||
+ | * Dave Sanderson will need to install the transit | ||
+ | - Install chiller and cooling water lines inside chamber. | ||
+ | * We can test these are leak tight by first pumping with them empty (water blown out with Nitrogen) and then fill with water and retest vacuum. No HiRA detectors inside chamber until this is complete! | ||
+ | * Once they have been leak tested these should never be disconnected. | ||
+ | - Test electronics with pulsers | ||
+ | - Remove dummies and replace with real telescopes. Align with transit. | ||
+ | - Setup and test ISEG bias supply | ||
+ | - test the Si detectors with alpha source | ||
+ | - test CsI with cosmics | ||
+ | - Install and align targets | ||
+ | - Set up the logic. | ||
+ | * The master trigger will likely be the CsI as last time. |