This shows you the differences between two versions of the page.
mar232012 [2012/03/23 14:59] rhodges created |
mar232012 [2012/03/23 15:07] (current) rhodges |
||
---|---|---|---|
Line 8: | Line 8: | ||
====Group Business==== | ====Group Business==== | ||
- | * Lab 127 available, but some stuff still in there and some changes not yet made: need pump exhaust pipes, sink, flammables cabinet.. | + | * Lab 127 available, but some stuff still in there and some changes not yet made: need pump exhaust pipes, sink, flammables cabinet... We won't move in until it's really ready |
+ | * TPC top plate coming in, will need to test the voltage--use miniball display case for safety | ||
+ | * Next week: Dan's practice talk | ||
+ | * No updates on Lee's schedule | ||
+ | |||
+ | ====Updates==== | ||
+ | * Mike: writing his paper, committee meeting this afternoon | ||
+ | * Dan: Neutron wall GEANT 4 simulation for Mike F. Starting to work on it. Also, looking at shadow bar mounts on spectra: the legs shadow neutrons | ||
+ | * Bec: PID offset in DE's for exp 06035. Examined punch-in and punch-through points, E is fine. DE has problems. Fit to energy? Will check out thickness. | ||
+ | * Rachel: Considering a switch to HiRA structure for files, from Mike's structure. We'll discuss at the Wednesday Analysis Meeting | ||
+ | * Jack: Efficiency program working with Mike's data, another version for Rachel' | ||
+ | * Zibi: Looking at Y, DR for (n/p) and (t/3He) in Ca data vs. pBUU vs. ImQMD. Different trends in each as vary Ecm and impact parameters |