14002:
Before vault:
Get pallets from storage (where do we put them? HiRA lab?)
Organize schedule with facilities to install chamber, TMP
Organize, assemble, test electronics (e.g. what kind of XLMs will we use?)
Remove dEs from telescopes
Test Es and decide on telescope arrangement
Plan out flange mapping
Will there be any detectors running at 2 gains like last time?
Procure an alpha source (does the lab have a new one yet?)
In vault:
Alignment (Dave Sanderson)
Install electronics (both Si and Csi), test with pulser
Clean chamber and get good vacuum
Flush and install chiller
Set up HV crate with proper bias mapping (with WU boxes probably)
Install telescope mount structure
Install telescopes, cable, hook up cooling carefully
Retest electronics (Si and CsI) with detectors connected, make sure everything biases properly
Test setup with alpha source
Setup targets
Align targets with telescope
14009:
Before 14002:
After 14002:
Remove telescopes, install dEs
Install dEs (maybe test them first, before removing them for 14002?)
Will we use a HiRA telescope at 0 deg? If so, we need a mount. If not, we need the detectors as well as a mount and proper electronics. Do we need to worry about radiation damage?
Install mount at 0 deg, associated electronics, and dE electronics/PA box
Install HiRA telescopes
Set up DE bias in HV crate
Test with alpha source
Make sure Si E and CsI electronics still set up properly