14002: Before vault:
-Get pallets from storage (where do we put them?)
-Organize schedule with facilities to install chamber, TMP
-Organize, assemble, test electronics (e.g. what kind of XLMs will we use?)
-Remove dEs
-Test Es and decide on telescope arrangement
-Plan out flange mapping
-Will there be any detectors running at 2 gains like last time?
-Procure an alpha source (does the lab have a new one yet?)
In vault:
-Alignment (Dave Sanderson)
-Install electronics, test
-Clean chamber and get good vacuum
-Flush and install chiller
-Set up HV crate with proper bias mapping (with WU boxes probably)
-Install telescope mount
-Install telescopes, cable, hook up cooling carefully
-Test setup with alpha source
-Setup targets
-Align
14009: Before 14002:
-Think about modifications for dE setup
-Test dE PA box (confirm how many PAs we have that work)
After 14002:
-Remove telescopes, install dEs
-Install dEs (maybe test them first, before removing them for 14002?)
-Will we use a HiRA telescope at 0 deg? If so, we need a mount. If not, we need the detectors as well as a mount and proper electronics. Do we need to worry about radiation damage?
-Install mount at 0 deg, associated electronics, and dE electronics/PA box
-Install HiRA telescopes
-Set up DE bias in HV crate
-Test with alpha source