Table of Contents
Beamline
Sending beam
Monitoring Beam
Turning things on/off
Startup / Shutdown
Opening/Closing Beam line Area
PDT & SDT
Ion Sources
FSEE
Links
FRIB Tasks
Beamline
Sending beam
Sending beam to a new destination
Setting DCCTs
Configuring MPS
Limiting primary beam power
Setting the attenuator threshold interlock
Monitoring Beam
Using the new beamloss threshold configuration tool
Using the Physics Calculator
Monitoring primary beam power
Monitoring ion sources
Monitoring charge strippers and Target
Monitoring Target IR Camera
Turning things on/off
Turning on/off SRF
Turning on/off
SCM
Startup / Shutdown
Starting up FRIB accelerator after maintenance shutdown
Shutting down FRIB accelerator
Opening/Closing Beam line Area
Target Facility Area
EXP Area
FRIB System Owning Departments and Breakdown Categories
PDT & SDT
PDT
SDT
Ion Sources
Performing a CSD
Recovering from a source trip
Recovering HPECR from Gate Valves Closing
FSEE
Stopping and starting beam for users to access tunnel
Procedure for setting up beam
Changing Flux
Viewer Transform
Links
FRIB Operational Safety Envelope