======= Closing Target Facility Areas ======= == Steps == - On the PPS rack, turn the room key to Search Survey. - Reset the warning alarms in area through the PPS rack. - Perform search and evict of area. - Once all target areas are secured, turn the Target RSS Ready for Beam key to Yes. Wait a minute for the Target Facility lights to stop flashing and turn solid red. - Ensure you are in required machine mode for beam. - Turn the Linac ACS key back to Beam Permit. - On the Main Magnets page, cycle the D5578 dipole to 90 A on the BBS/FFS tab: - Copy the current setpoint value. - Turn on D5578 dipole (this will take a few seconds to go green). - When the dipole is on, input 90 A into the setpoint value. - When done ramping to 90 A, let it sit for about a minute. - Paste the original setpoint value and set the magnet to it. - Wait for dipole to ramp to original value. - On the MPS Operator page, turn the E-Bends on. - On the Main Magnets page check that the E-Bends setpoint and readback values match on the V-LEBT tab. - On the MPS Operator page, set configuration according to MPS Device Configuration Guideline. - Check and clear all set MPS devices. - Start the Chopper. ===== Links ===== * [[clist>154|Search-and-Evict Procedure for the FRIB Target Hall]] * [[dcc>WBS=S30103&Sub=RC&SN=008105|MPS Device Configuration Guideline]]