| - | == Steps == | + | == Open == |
| - Turn the Beam/ | - Turn the Beam/ | ||
| - On the Main Magnets page, turn Dipole D5578 off on BBS/FFS tab; this will take a moment to ramp down to 0 A. | - On the Main Magnets page, turn Dipole D5578 off on BBS/FFS tab; this will take a moment to ramp down to 0 A. | ||
| Line 9: | Line 9: | ||
| - Operator goes to room and starts a survey for entire area, or specific spot if required. | - Operator goes to room and starts a survey for entire area, or specific spot if required. | ||
| - After room fully surveyed and opened, on the PPS rack, turn the key for the opened room to Regulated Access. | - After room fully surveyed and opened, on the PPS rack, turn the key for the opened room to Regulated Access. | ||
| + | |||
| + | == Close == | ||
| + | |||
| + | - On the PPS rack, turn the room key to Search Survey. | ||
| + | - Reset the warning alarms in area through the PPS rack. | ||
| + | - Perform search and evict of area. | ||
| + | - Once all target areas are secured, turn the Target RSS Ready for Beam key to Yes. Wait a minute for the Target Facility lights to stop flashing and turn solid red. | ||
| + | - Ensure you are in required machine mode for beam. | ||
| + | - Turn the Linac ACS key back to Beam Permit. | ||
| + | - On the Main Magnets page, cycle the D5578 dipole to 90 A on the BBS/FFS tab: | ||
| + | - Copy the current setpoint value. | ||
| + | - Turn on D5578 dipole (this will take a few seconds to go green). | ||
| + | - When the dipole is on, input 90 A into the setpoint value. | ||
| + | - When done ramping to 90 A, paste the original setpoint value. | ||
| + | - Wait for dipole to ramp to original value. | ||
| + | - On the MPS Operator page, turn the E-Bends on. | ||
| + | - On the Main Magnets page check that the E-Bends setpoint and readback values match on the V-LEBT tab. | ||
| + | - On the MPS Operator page, set configuration according to MPS Device Configuration Guideline. | ||
| + | - Check and clear all set MPS devices. | ||
| + | - Start the Chopper. | ||
| + | |||
| + | |||
| + | |||
| + | ===== Links ===== | ||