This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision Next revision | Previous revision | ||
|
venting_pumping_object_box [2024/02/06 09:37] noji |
venting_pumping_object_box [2025/12/01 12:37] (current) pereira [Vent Object chamber] |
||
|---|---|---|---|
| Line 1: | Line 1: | ||
| ====== Venting/ | ====== Venting/ | ||
| - | ===== Vent Object chamber ===== | + | In CS-Studio/ |
| - | + | ||
| - | From the S800 Main Vacuum page, go to the Object chamber page, opening the page shown in the figure | + | |
| {{: | {{: | ||
| + | |||
| + | ===== Vent Object chamber ===== | ||
| The vent valve and the roughing valve RV should be closed when you begin. | The vent valve and the roughing valve RV should be closed when you begin. | ||
| The venting procedure is as follows: | The venting procedure is as follows: | ||
| - | - Notify the Control Room and inform them that they can disregard the EXP alarm that will occur | + | - Notify the Control Room and Vacuum Group and inform them that they can disregard the EXP alarm that will occur |
| + | - Make sure that the detectors inside the chamber have been unbiased | ||
| - Close the beamline gate valves D2341 BGV and D2303 BGV | - Close the beamline gate valves D2341 BGV and D2303 BGV | ||
| - Turn off the IG | - Turn off the IG | ||