This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
shutdown_s800_s3_vault [2020/11/06 14:46] pereira |
shutdown_s800_s3_vault [2024/02/20 03:10] (current) pereira [S3 Vault] |
||
---|---|---|---|
Line 114: | Line 114: | ||
* Leave vault unsecured and fully accessible | * Leave vault unsecured and fully accessible | ||
* Put signs in S3 and S2/S3 doors indicating that "S3 vault is under emergency shutdown"; | * Put signs in S3 and S2/S3 doors indicating that "S3 vault is under emergency shutdown"; | ||
- | * Jorge Pereira (S3 vault coordinator, | + | * Jorge Pereira (S3 area coordinator, |
- | | + | |
- | * Antonio Villari | + | |
- | * Daniel Bazin (S800 Senior Device Physicist | + | |
- | * Remco Zegers (Magnetic Spectrometer group leader) | + | |
==== Electronics and computers ==== | ==== Electronics and computers ==== | ||
Line 134: | Line 133: | ||
- | |||
- | |||
- | |||
- | |||
- | |||
- | |||
- | ===== Communication before and after completion of Shutdown ===== | ||
- | * Give heads up to Operations (beam coordinator) | ||
- | * Heads up to any experimenters planning to run in the vault | ||
- | * Heads up to GRETINA group | ||
- | * Heads up to Cryogenics group | ||
- | * Heads up to Magnet group | ||
- | * Make an entry in Hourlog indicating status of S800. Include also contact information. | ||
- | * If possible, prepare and submit a Work-Control Plan | ||
- | |||
- | |||
- | ===== Detectors ====== | ||
- | * Turn off all GUI-controlled HV (including iSeg HV for hodoscope (crystal #20), located in S3 crate attached to FP chamber) | ||
- | * Turn off power supply preamps and CRDC interface boards (same S3 crate attached to FP chamber) | ||
- | * Turn off all manual HV in dU6 (OBJ SCI, CRDCs grid) | ||
- | * Empty detectors and make sure that valves configuration matches " | ||
- | * Close gas bottles and valves downstream of regulators | ||
- | |||
- | |||
- | ===== Drives ===== | ||
- | * Retract all linear drives | ||
- | * Open beam blockers | ||
- | |||
- | |||
- | ===== Vacuum ===== | ||
- | * Close ALL gate valves | ||
- | * VERY IMPORTANT: Vent FP box, but leave dry N2 flowing (it requires opening the lift-off disk of the pressure-relief valve) | ||
- | * Make sure that FP Turbo-pump is OFF. Turn OFF Turbo Pump chiller | ||
- | * Turn off CRDCs chiller | ||
- | * Vent all sections, including Spectrograph (assistance from vacuum group will be needed). IF this is not possible, make sure that this section is isolated (close gate valves upstream and downstream) | ||
- | * Make sure that all sections are at atmospheric pressure | ||
- | |||
- | |||
- | ===== Magnets ===== | ||
- | * Set all Brhos to 0 Tm | ||
- | * Turn off all power supplies, including steerers | ||
- | |||
- | ===== Cryogenics ===== | ||
- | * Notify (e.g. email) Cryogenics that all magnets are off | ||
- | * Check if there is any He lead return pipe open. If so, notify Magnet group and/or Cryogenics group so they can close it at their earliest convenience | ||
- | |||
- | |||
- | ===== Electronics and computers ===== | ||
- | * Turn off all crates in S800 rack (S3 vault) | ||
- | * Turn off all crates in dU6 | ||
- | * Reboot s800fp PC (in S3) | ||
- | * Reboot down u6pc5 | ||
- | * Reboot down spdaq50 | ||