This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision | |||
|
installation_fp_sci [2025/12/01 12:34] pereira [Emptying Detectors] |
installation_fp_sci [2025/12/01 12:34] (current) pereira [Venting FP Chamber] |
||
|---|---|---|---|
| Line 34: | Line 34: | ||
| ===== Venting FP Chamber ===== | ===== Venting FP Chamber ===== | ||
| - | Notify the Control Room that you will vent the FP chamber. | + | Notify the Control Room and Vacuum Group that you will vent the FP chamber. |
| - Ensure the IG in the Focal Plane Pumping Station is off. This page can be found in FRIB EXP Main → S800 → Vacuum Main (Primary Pages) → Focal Plane. | - Ensure the IG in the Focal Plane Pumping Station is off. This page can be found in FRIB EXP Main → S800 → Vacuum Main (Primary Pages) → Focal Plane. | ||